On 27.03.2019, an agreement was signed between Przedsiębiorstwo Energetyki Cieplnej Sp. z o.o. with its seat in Mińsk Mazowiecki and the consortium of companies Introl-Energomontaż Sp. z o.o. with its seat in Chorzów and Ferox Energy Systems Sp. z o.o. with its seat in Katowice on the project implementation called “The construction of a heat and power plant in Mińsk Mazowiecki”.

The subject of the Agreement is a complex construction of a gas heat and power plant (EC) located in Mińsk Mazowiecki, equipped with two high performance gas cogeneration units, each with the following output parameters: electric power of ca. 3.3 MW and heat power of ca. 3.1 MW and heat accumulator with capacity of approx. 38.2 GJ. The heat and power plant shall be powered with methane-rich gas (E-type). Produced electricity will be transferred to the electricity transmission grid of the distribution system operator using 15kV cable line. Produced heat will be transferred to the heating grid. Planned investment completion date: 06.2020.